Connecting to our Grid

Please review our Customer-Owned Generation page before making a decision to invest in an electric generation system—like solar. If you decide to move forward with your own system, follow these steps to start the process to connect to MGE's electric grid. 

1. Complete, sign and send the following:

  • Application—Effective August 1, 2024, any application to connect to MGE's electric grid must use the newly approved 6031 Application form (Wisconsin Standard Distributed Generation Application Form). Any Interconnection Agreements must use the correct version of Form 6029/6030 with an effective date of 05/01/24, as denoted in the top left corner of the agreement under the State Seal. Please use the forms at the links provided below.
  • Line diagram of your system.
  • Proof of insurance certificate.
  • Minimum application review fee
    • Effective August 1, 2024, any Interconnection Application submitted to MGE will be subject to the Application Review and Commissioning fees based on the specified category and kilowatts (kW) as detailed in the tables below. 
    • Along with your initial application, you will be required to pay a minimum application fee, as defined in the associated table, based on your Category.
      1. At this time, MGE is only accepting physical checks. The project installation address must be included and clearly indicated on the check in the memo line. If it is not included, the check will be returned to you for the required information. 
      2. Each installation address is considered a single request. Multiple installations cannot be combined into one check and will need to be paid per individual application.
      3. Application materials must be submitted electronically through mgeDGAdmin@mge.com or via U.S. mail.
 Table 119.08-1
CategoryExport CapacityApplication Review FeeEngineering Review FeeDistribution Systems Study FeeCommissioning Fee
120 kW or less$150 (1-8 kW)
$300 (9-20 kW)
Cost basedCost based$150
2Greater than 20 kW to 200 kW$300 + $10/kWCost basedCost based$250
3Greater than 200 kW to 1 MW$2,000 + $2/kWCost basedCost based$1,000
4Greater than 1 MW to 15 MW$4,000 + $0.50/kWCost basedCost based$2.500


Minimum Application Review Fees
Category
Export CapacityMinimum Application Review Fee
11-8 kW$150
19-20 kW$300
2Greater than 20 kW to 200 kW$300
3Greater than 200 kW to 1 MW$2,000
4Greater than 1 MW to 15 MW$4,000

2. It is highly recommended that you also sign and send, but do not fill out, the Standard Interconnection Agreement. Sending this early will help to expedite the process.

3. Once your application and other supporting documents have been approved, order and install your equipment.

4. Have your system inspected and approved by your municipality's electrical inspector.

5. MGE will call you to schedule an appointment for inspection, testing and interconnection after we receive the permit from the inspector. NOTE: If your system is residential and photovoltaic (PV) only, then we will need photos of the completed system instead of scheduling an appointment. Photos can be submitted at any time after the system has been installed and should contain the following:

  • Photos of each inverter installed in order to confirm they are UL1741 rated and that their sizes match the interconnection application and drawing. If using microinverters, these photos are not necessary.
  • A single photo including both the disconnect switch and the meter socket to verify the location of the disconnect switch. If the meter is inside, then show the disconnect switch next to mast/LB entering the house.
  • A single photo of the inside of the disconnect switch in order to confirm if the blade is fused or solid.

6. Once the electrical permit has been received, the associated Commissioning fees and any other remaining fees have been paid (see Table 119.08-1) by check, and we have either commissioned your system in person or approved the submitted photos of your system, you will receive an official email authorizing you to begin operation of your system.

  • Any remaining fees after payment of your initial minimum Application Review Fee will be detailed in the standard Application Approval email sent to you when your application materials have been approved.
    • At this time, MGE is only accepting physical checks. The project installation address must be included and clearly indicated on the check in the memo line. If it is not included, the check will be returned to you for the required information. 
    • Each installation address is considered a single request. Multiple installations cannot be combined into one check and will need to be paid per individual application.
     

Electric rates

The credits you are eligible to receive depend on the size of your system:

Contact information

We can receive materials via email or standard mail. If you have questions about the application or installation process, rates or systems, please contact us.

Email: mgeDGAdmin@mge.com

Phone: 608-252-4783

Mail: Administrative Support, Madison Gas and Electric, PO Box 1231, Madison, WI  53701-1231

For more information

Considering Rooftop Solar?

Do your homework before you invest in your own system.

See our tips

Clean Energy Programs

See how you can support local renewable energy. No installation required!

Explore programs
Madison Skyline